W08D1 – More Daring Drains and walls going up…..
Looks like the Arco-drain out the front is a no-no – electricity and gas pipes are not deep enough to allow this drain to be built so builders are going to put 2 gulleys in to take the storm water through to the rear of the property.
Work commenced upon the retaining wall element, there is a little worry that we are not going to get the size we want in the utility room to allow us to have washer and dryer in the room – explained that was the sole purpose of the room and they needed to make it work whatever – this was not a point that was up for negotiation. We have decided to put a smaller door in the back, move the lintel to the left close to the retainer and this gives us the room we need.
Had GorillaGrass over to discuss work in the rear of the property. Quote of £3500 to do the 64 sqm. in artificial grass.