W20D2 – More patio, frames and insulation.

Well today was a bit dryer, however Tim turned up in his waterproofs as he was going to spend another day in the mud laying huge slabs on oceans of mortar 😉  The majority of the return and patio door are was completed today and again we have to keep our asses off it until it dries.

Inside, the walls for the bathroom are plaster-boarded and the cuts for the sockets and spots have been cut into the board ready for plastering tomorrow.

Managed to order some shower panels for the bathroom and they should be delivered Friday with any luck, but then again, so will all the bathroom furniture so need to make some space in the box.

The shower and screen are due to be delivered tomorrow.