W14D5 – Internal Walls and waiting for trusses…

Today was a little wetter than the last couple of days and the brickies managed to get the block work on the gable up to a level to expect trusses and then they worked on the internal wall of the utility room.  The chap for the windows and doors turned up today and left a couple of brochures for doors.  I spoke to builder and we sorted that we will have roller garage door – possibly automated to give better security; Only another £150…